22nd April, 2026

Does CDM 2015 Apply To Demolition?

When, and how, does CDM 2015 apply to demolition work? As in, projects that don't involve any new construction. Demolition might involve breaking down walls, dismantling structures, removal, and site clearance. So if you're not building or constructing, but rather removing and dismantling, does CDM apply?

Does CDM 2015 Apply To Demolition? header image

The Construction (Design and Management) Regulations (CDM) apply to construction work, but what about demolition? After all, demolition work doesn't involve constructing anything. You're not putting up, but pulling down.

For projects that don't involve any new construction, just removal and site clearance, does CDM apply?

CDM applies to demolition work

The simple answer is, yes, CDM does apply to demolition projects.

CDM applies to all construction work. And while you may think there is an argument that demolition doesn't involve constructing anything, it does fall into the definition of construction work under CDM.

The definition of construction work under CDM 2015 is far-reaching, and one paragraph in particular deals with demolition…

2.—(1) 'construction work' means the carrying out of any building, civil engineering or engineering construction work and includes — ... (b) the preparation for an intended structure, including site clearance... (d) the removal of a structure, or of any product or waste resulting from demolition or dismantling of a structure...

The Construction (Design and Management) Regulations 2015 Interpretation

And this shouldn't come as a big surprise. After all, demolition work is within the construction industry. And demolition work is often involved in the early stages of a construction project.

It's fair to say that most construction projects will have some kind of demolition, strip-out or clearance works involved.

Oh, and just in case you're thinking a structure only applies to an office, house or another form of building, it doesn't. The definition of a structure under CDM covers anything from a tramway line, sewer and earthworks, to fixed plant and scaffolding and everything in between and similar.

contractor on railway

So whatever it is you are taking down, removing, clearing, or demolishing, whether it's a building, machine, temporary structure, or some other structure, it comes under the definition of construction work under CDM.

And that means that everyone involved in the project needs to apply the duties and responsibilities of CDM.

Essentially, if you are working on a project involving demolition work, you need to apply CDM.

Small demolition projects

But what if the work is short? What if it will only take a couple of days? Or even less than a day? Maybe a week, but it will definitely last less than 30 days? Isn't 30 days the notification threshold? So if you're under that, CDM doesn't apply?

No, no, and no!

demolishing a wall

CDM still applies in full, to all construction projects, no matter how big or small, how long or short.

Don't risk breaches, fines and prison time - complying with CDM is a legal requirement.

Even if you are under the CDM notification threshold, CDM still applies in full. The only thing that you may not need to do is notify the HSE (if under 30 days with 20 workers and also under 500 person-days). But all other CDM duties still need to be complied with.

CDM duties for demolition work

Since demolition work comes under the definition of construction work for CDM, all the usual CDM duties apply.

This means that your demolition project will need the appointment of the principal contractor and principal designer, where there will be more than one contractor involved (including subcontractors).

principal contractor appointment flowchart

A construction phase plan will need to be produced by the principal contractor (or contractor if only one), and the pre-construction information will need to be provided by the client.

And of course, contractors are going to need pre-construction information. They will need to know the location of any hazardous materials like asbestos, and the presence of any services, particularly underground or hidden services that may not be immediately obvious.

Demolition-specific CDM requirements

In fact, in addition to the usual CDM requirements, the regulations have a little something extra to say about demolition work, tucked away in the less talked about, but just as important, Part 4 of the CDM regulations.

20.—

  1. The demolition or dismantling of a structure must be planned and carried out in such a manner as to prevent danger or, where it is not practicable to prevent it, to reduce danger to as low a level as is reasonably practicable.
  2. The arrangements for carrying out such demolition or dismantling must be recorded in writing before the demolition or dismantling work begins.

Nothing especially exciting here, and the first statement fits in well with the normal health and safety requirements to risk assess and apply the principles of prevention. Since employers have legal health and safety responsibilities to prevent harm in any workplace, this should be standard practice - especially on a high-risk construction site.

excavating ground

However, when we look down at the second item, there is a specific requirement to record a demolition plan in writing before starting any demolition or dismantling works.

Only projects involving demolition work need a demolition plan. This is an additional health and safety requirement because if demolition work isn't properly planned, and, for example, things are done in the wrong order or without the correct support, an uncontrolled collapse could put lives in danger. The aim of CDM, after all, is to make construction work safer.


It is clear when looking through the CDM regulations that demolition work comes well within the scope. It's specifically mentioned within the definition of construction work, and even has its own section in Part 4 of the CDM regulations. This makes sense since demolition work is one of the highest-risk activities in construction.

No matter the size or duration of the project, or what type of structure, yes, CDM 2015 does apply in full to demolition works.

Want to check if your construction project complies with CDM? Use our free CDM compliance checklist.

share on twitter share on facebook share on linked in share by email

This article was written by Emma at HASpod. Emma has over 10 years experience in health and safety and BSc (Hons) Construction Management. She is NEBOSH qualified and Tech IOSH.

Need CDM Help?

Get CDM support on your construction projects with our free guides and support packs for all duty holders.

CDM Support

Recent posts like this...

Does CDM 2015 Apply To Demolition? image

Does CDM 2015 Apply To Demolition?

When, and how, does CDM 2015 apply to demolition work? As in, projects that don't involve any new construction. Demolition might involve breaking down walls, dismantling structures, removal, and site clearance. So if you're not building or constructing, but rather removing and dismantling, does CDM apply?

Read Post
The A-Z Of CDM Design Risk Assessment For Architects image

The A-Z Of CDM Design Risk Assessment For Architects

As a designer on a construction project, what risks should you assess to comply with the CDM regulations? In this post, we will go through the A-Z of CDM design risk assessment, giving you 26 areas to think about when considering health and safety in your design.

Read Post
CDM 2015 Documents Explained image

CDM 2015 Documents Explained

There are several documents required under CDM 2015. In this blog post, we look at which documents are needed - and when. CDM 2015 has been around for a while, and the regulations apply to all construction projects in Great Britain. So, what documents do you need for your construction project?

Read Post

Spend less time on paperwork.
Start with the free plan today.